Elaboration of P-stage documentation.
20 Dec 2011
Act of Permitted Usage is obtained.
P-stage documentation is elaborated and approved .
Mosgosexpertiza approval is obtained.
Set of documents is preparing for obtaining of Constructon Permit.
02 Oct 2009
Architechtural-planning solutions are developed.
City Planning Verification is worked out and approved by Moskomarchitectura.
Act of Permit Usage is issued.
Elaboration of P-stage documentation is completing.
02 Oct 2009
Design documentation is approved by MosGosExpertiza.
Construction Permit is formalized.
Working documentation (WD) on the construction of substructure is elaborated. Elaboration of WD on the construction of superstructure is completing. Designing of internal engineering systems is ongoing.
General Contractor is appointed.
Construction site and cabins are arranged. Tower crane is mounted.
Construction of substructure is ongoing. Construction of foundation is completed. 2nd floor containing walls are erected.
01 Oct 2009
Construction Permit is obtained from MosGosStroyNadzor.
Demolition of all buildings and structures are completed.
Holding a tender of general contractor is ongoing.
30 Sep 2009
Commissioning Certificate on the whole complex is formalized.
Landscaping of the territory and around is ongoing.
30 Sep 2009
Architectural-planning solutions are developing at the moment.
30 Sep 2009
Architechtural-planning solutions are developed.
City Planning Verification is worked out and approved by Moskomarchitectura.
Act of Permit Usage is issued.
Elaboration of P-stage documentation is completing.
29 Sep 2009
Design documentation of P-stage is approved by Mosgosexpertiza.
Preparation on holding a tender of general contractor is ongoing.
29 Sep 2009
DC-group is looking for well-educated, energetic young men to the position of the project manager.